PIR insulation
BauderPIR T under the covering: how the slope of the entire roof is created
At a glance
BauderPIR T has no factory-applied facing, so its surface must not be equated with the foil on an aluminium-faced board. The method of constructing the covering must follow from the correct roof solution. At the same time, the tapered boards are responsible for the geometry, and the covering for watertightness. These functions must be checked separately and combined in a single cross-section. The cross-section under consideration covers a roof with unfaced tapered insulation boards. The role of BauderPIR T must be described together with the layers adjoining its surface. An important junction point is the roof valley conducting water towards the outlet. The basis for agreement is the slope drawing with the direction in which the thickness increases. Before selecting materials, the levels of the substrate and the course of the water-collecting lines must be established so that the sequence of layers has a real reference.

Function of the board in the cross-section
A correct layout should make it possible to obtain the required drainage path and the correct thermal section. The tasks of the remaining layers must be defined separately.
The correct product and the scope of its data
In the article on the slope of the whole roof, BauderPIR T is the layer that shapes the geometry, not the covering. The manufacturer states a format of 1200 × 800 mm, straight edges and slopes from 1% to 5% in increments of 0.5 percentage points; 2% is one of the variants. The declared reaction to fire is E, and the compressive strength is at least 120 kPa. The thermal values relate to this variant and the relevant thickness, not to the aluminium-faced BauderPIR FA. The PIR core has no factory facings, which is why its surface requires separate treatment in the section.
Scope of the example comparison
Example: a 2.40 m section at a constant slope of 2.00% gives a height difference of approximately 48.0 mm. This is a geometry calculation, not the thermal resistance of the roof. The documentation for the BauderPIR T family confirms such a slope value, but the example does not define the entire field or the starting level. The level at the outlet depends on the substrate and the underlying layers, and the course of the joint changes in the roof valley leading water towards the outlet. Base the inspection before covering on the slope drawing with the direction of increasing thickness, covering all sections.
The calculation involving BauderPIR T describes the stated quantity, not automatically the class of the entire system. The key assumption is the range of slopes from 1% to 5% in increments of 0.5 percentage points. The result must be compared with the limitation defined as the correct assignment of each wedge to its place in the plan. With regard to this section, the valley line and the outlet level must be compared with the actual geometry of the substrate. A slope drawing with the direction of increasing thickness is helpful, from which the position of each layer follows. Only then can the waterproofing covering be considered in a confirmed roof solution without implicitly transferring rules from another combination of materials.
How to assess the proposed change
The variant based on the decision to lay the designed tapered boards on the surveyed substrate must be considered through the full section. In the second step, the following action must be considered: changing the falls plan after establishing different elevations. With BauderPIR T, both proposals must preserve the requirements at the location described as the roof valley directing water towards the outlet. It must be ruled out to treat the nominal taper of the board as confirmation of drainage across the entire roof slope, because such a simplification changes the basis of comparison. The final scope should be confirmed by the falls layout designer. For the selected solution, a schedule of taper board types with quantities for each drainage field is required, consistent with the materials located directly below and above the insulation.
Surface and joint finish
The surface of BauderPIR T is the exposed PIR surface without factory facing. Its type must be taken into account when selecting the layer with which it will work. In the documentation, the plain edge of the unfaced taper board must also be identified, instead of replacing the actual geometry with a general symbol. Acceptance should be based on the record of taper board markings and elevation measurements before covering. For this reason, the waterproofing covering in the confirmed roof solution should only be installed after the agreed inspection. In the drawing, it is worth highlighting the roof valley directing water towards the outlet, because that is where the course of the connection changes.
The sequence of works follows from the layout
Before laying BauderPIR T, a substrate consistent with the geometry of the falls system must be ensured. The schedule should include inspection of the element described as the roof valley directing water towards the outlet. For acceptance, a falls drawing with the direction of increasing thickness must be prepared, indicating any execution changes. After this inspection, work can proceed to the scope that is the waterproofing covering in the confirmed roof solution. The sequence should be agreed under the lead of the falls layout designer, especially when different layers are installed by different teams. This allows the tasks of the polyurethane insulation to be separated from the works providing the other functions of the section.
A specification ready for pricing
An enquiry for BauderPIR T should clearly indicate a roof with unfaced taper boards. The description must include a schedule of taper board types with quantities for each drainage field, so that the supplier knows the adopted variant. A separate item may be the work required to achieve the required drainage path and the correct thermal section. It is worth requesting a breakdown of changes caused by any replacement of facing or geometry. Each such proposal should again take into account the correct assignment of each taper board to its location in the plan. After selecting the solution, the record of taper board markings and elevation measurements before covering must be retained as the basis for identifying the material on site. In such an order, the polyurethane boards are part of a specific system, not a category of freely interchangeable sheets.
7 branches. Materials closer to your project.