At a glance

When a hall is being refurbished, the first question is often how many panels to order. Before drawing up a schedule, sketch the existing walls and roof and mark exactly where the replacement work will end. A large door, a rooflight or the junction with a later extension can change the number and type of flashings needed. In Building basics on Sandwich-panel.pl you will find a guide to surveying a hall before recladding it with PIR sandwich panels. Start with one elevation and a list of questions for the contractor, then work around the rest of the building.

What belongs on an elevation sketch?

Number the openings and match each number to a photograph. Distinguish doors and windows that will stay from those being replaced. At each junction between the old and new cladding, record who will assess the detail.

How do you arrange a survey in a working hall?

Agree access to the walls with the operator and identify times when each area can be inspected. In the survey notes, separate actual measurements from areas you could not reach so they can be measured later.