PIR insulation
BauderPIR FA-TE in a terrace: sequence and tasks of the layers
At a glance
A terrace with FA-TE comprises insulation, waterproofing and the use layers. The support for the surface can transfer force to a much smaller area than the surface of the entire board. Such an arrangement requires a separate assessment of the pressure and protection of the covering. The PIR compression parameter does not replace the design of the solution above the insulation. The cross-section under consideration comprises the thermal insulation of the terrace above a room. The task of BauderPIR FA-TE must be described together with the layers adjoining its surface. An important junction is the threshold of the terrace door and the nearby drain. The basis for agreement is the terrace cross-section at the door with the marked levels. Before selecting materials, the distance between the substrate and the permissible level of the surface must be determined so that the sequence of layers has a real reference.

Function of the board in the cross-section
The correct layout should allow the thermal insulation to fit together with the drainage and the terrace finish layers. The functions of the remaining layers must be defined separately.
The correct product and the scope of its data
In the terrace cross-section above a room, BauderPIR FA-TE is a factory-made board in which the PIR core works together with aluminium facings — the values λD 0.022 W/(m·K), CS(10/Y)120 and reaction-to-fire class E refer to the product formed in this way, not to the foam alone. The external dimension of 1200 × 600 mm, straight edges according to the British documentation and the installation dimension of 1185 × 585 mm from the Polish data sheet, as well as the designation FA TE F with rebate, are separate variants; they are not combined without confirmation for the specific delivery, because a different geometry changes the way they are laid relative to the waterproofing and the surface supports.
Scope of the example comparison
For a terrace with BauderPIR FA-TE, compare the insulation height together with the pressure from the surface and supports. An example for 100 mm, λ 0.022 and the calculation d/λ gives approximately 4.55 m²K/W. With a hypothetical lambda of 0.040, this would correspond to a layer of approximately 181.8 mm; these are not declared data of another product, and the calculated resistance is not a declared RD. The edge profile must correspond to the documentation of the specific delivery. Only after checking the distribution of pressures, the facings and the fixing can the change to the entire terrace cross-section be assessed.
The calculation involving BauderPIR FA-TE describes the stated value, not automatically the class of the entire system. The relevant assumption is the small external format of 1200 × 600 mm. The result must be compared with the limitation defined as the height limit below the threshold with the required finish. With regard to this cross-section, the height of the surface, insulation and drainage must be compared on one cross-section. A terrace cross-section at the doors with marked levels is helpful, from which the position of each layer can be seen. Only then can the terrace finish with waterproofing and surface be considered without automatically transferring the rules from another combination of materials.
How to assess the proposed change
A variant based on the decision to change the thickness of the thermal layer while maintaining the required effect must be considered through the full section. In the second step, the action to be considered is: redesigning the remaining terrace heights. With BauderPIR FA-TE, both proposals must preserve the requirements at the location described as the terrace door threshold and the nearby drain. A combination of the simple UK variant’s data with a Polish datasheet with a smaller cover width must be excluded, because such a simplification changes the basis of comparison. The final scope should be confirmed by the terrace designer together with the door connections. For the selected solution, an FA-TE description is needed covering the specific edge variant, consistent with the materials located directly below and above the insulation.
Surface and joint finish
The surface of BauderPIR FA-TE is an aluminium facing with an auxiliary mesh in the variant described. Its type must be taken into account when selecting the layer with which it will work. In the documentation, the edge profile confirmed for the selected documentation and delivery must also be identified, instead of replacing the actual geometry with a general symbol. Acceptance should be based on the document confirming the edge and the delivery’s installation dimension. For this reason, the terrace finish with waterproofing and surfacing should only be carried out after the agreed inspection. In the drawing, it is worth highlighting the terrace door threshold and the nearby drain, because that is where the course of the connection changes.
The sequence of works follows from the build-up
Before BauderPIR FA-TE is laid, the distribution of pressure from the surfacing and its supports must be ensured. The schedule should include inspection of the element described as the terrace door threshold and the nearby drain. For acceptance, a terrace section at the door with marked levels should be prepared, indicating any execution changes. After this inspection, work can proceed to the scope that is the terrace finish with waterproofing and surfacing. The sequence should be coordinated by the terrace designer together with the door connections, especially when different layers are carried out by different teams. This makes it possible to separate the tasks of the polyurethane insulation from the works ensuring the other functions of the section.
Specification ready for pricing
An enquiry for BauderPIR FA-TE should clearly indicate thermal insulation of the terrace above a room. The description should be accompanied by an FA-TE description covering the specific edge variant, so that the supplier knows the adopted variant. A separate item may be the work needed to accommodate the insulation together with drainage and the terrace finish layers. It is worth asking for a breakdown of the changes caused by any replacement of the facing or geometry. Each such proposal should again take into account the height limit below the threshold with the required finish. Once the solution has been selected, the document confirming the edge and the delivery’s installation dimension must be kept as the basis for identifying the material on site. In such an order, the polyurethane boards are part of a specific system, not a category of freely interchangeable sheets.