XPS between a hall and an office: detailing the floor junction

At a glance

An office within a hall is often heated continuously, while the warehouse operates at a lower temperature. Both parts may also have different loads and floor levels. XPS helps to limit heat losses, but at their junction a well-thought-out detail is needed. Extruded polystyrene should not be selected separately for each room without checking the connection. It is precisely at the threshold, under the wall and next to the column that a discontinuity in the insulation can arise. The wall between the office and the hall may separate zones with different temperatures. In such a case, the heat flow does not end at the plane of the wall. It also covers the floor, its edge and structural elements.

Light green XPS boards standing upright and stacked, various edges visible

First, the thermal boundary is defined

Before laying the XPS, it is necessary to establish which surfaces form the envelope of the heated part. This makes it possible to plan the continuity of the insulation without accidental gaps.

If both zones have a similar temperature, the justification for certain details may be different. However, such conditions should not be assumed solely on the basis of the current way the hall is used. XPS should be selected according to the planned use. Extruded polystyrene hidden beneath the floor is difficult to change later, when the warehouse is cooled or the office starts operating around the clock.

Different loads mean different floors

The office is subject to different loads than the forklift route or beneath the racking. The load-bearing layer and the requirements for the XPS may therefore differ. It is not necessary to automatically use one grade throughout the entire building. It is, however, necessary to check how the transition between the systems will be resolved. A change in thickness or in the stiffness of the support should not be hidden in an undescribed strip next to the wall.

Extruded polystyrene is selected for the loads together with the floor structure. A high compressive stress value on the label does not replace checking creep or permissible displacements. The XPS under the office may meet different requirements than under the hall, but both parts must maintain correct performance of the connection. This applies in particular to the doors through which transport takes place between the zones.

Levels must be coordinated before installation

The office often has a different finish planned than the hall. Additional installation layers, underfloor heating or a different screed may be present. Equal finished floor levels therefore do not mean equal XPS thickness. First, all layers of both cross-sections are compared. Only then is the substrate level and the position of any steps determined.

The door threshold requires stable support and a proper connection to the floor. A heavy element should not be rested on a random strip of XPS without checking how forces are transferred. If trolleys pass through the opening, edge pressures must also be taken into account. An error in this zone often shows up as cracking of the finish or a change in level, rather than as visible damage to the insulation itself.

A partition wall does not always stand on the screed

The position of the wall’s foundation depends on its construction and the design. A heavy partition should not be placed arbitrarily on a floating screed. If the wall extends into the structural layer, it can interrupt the thermal insulation. In that case, the XPS at its base must be resolved in accordance with the detail analysis. It is not enough to push the boards together from both sides and assume that the heat flow path has been closed.

Extruded polystyrene also does not replace the acoustic insulation provided for in the office floor. High rigidity and resistance to pressure do not indicate impact sound attenuation. XPS can perform the thermal task, while acoustic requirements need a separate solution. At the junction between the hall and the ancillary areas, it is worth considering both problems so that improving one parameter does not obscure the other.

Moisture and services at the boundary between rooms

Water from cleaning the hall should not pass freely into the office floor layers. The low water absorption of XPS is helpful under certain conditions, but it does not create a sealed threshold. Protection against water is designed together with falls and drains. It is also worth checking whether the junction of the floors is located in a place where moisture regularly accumulates.

Penetrations of conduits through a wall or floor must retain the required protection. The XPS layout is adapted to the planned routes instead of filling the remaining space after pipes have been laid at random. This applies both to thermal continuity and to the support of the floor. It is worth showing the openings and chases on a shared drawing available to the construction team and the installers.

One detail for all contractors

XPS is produced by, among others, Synthos, Finnfoam and swisspor. When selecting, the thickness, parameters and intended use of the boards in each zone must be specified. The name styrodur alone does not allow these requirements to be distinguished. The delivery should be labelled so that the team does not swap materials between the office part and the industrial part. A simple layout plan reduces the risk of such a mistake.

At the acceptance inspection, the run of the XPS at the wall, the threshold and the columns is checked, as is the conformity of the levels. Extruded polystyrene is best assessed before it is covered, when all the joints are visible. A well-resolved junction does not have to be complicated. It must, however, correspond to the temperature difference, the loads and the actual construction of the floors. Such a detail makes later use of both parts of the building easier without costly corrections.

7 branches. Materials closer to your project.

Sandwich-panel.pl map of seven branches offering sandwich panels, PIR boards and sheet metal
  • SEROCK — Dzierżenin 34 E [mapa]
  • BŁONIE — ul. Sochaczewska 138A [mapa]
  • RADOM — ul. Grobickiego 8 [mapa]
  • ŁÓDŹ — Natolin 8 [mapa]
  • OLSZTYN — Barczewo, ul. Prosta 9 [mapa]
  • WROCŁAW — ul. Jerzmanowska 10C [mapa]
  • GORZÓW WLKP. — ul. Zielona 33/34 [mapa]

Check prices and availability: +48 500 409 109

Free quote