Eurothane G in the loft: internal insulation and layer junctions

At a glance

In a loft, wall insulation must work together with the insulation of the roof slopes. Eurothane G should not end in a random gap at the slope. Designing this junction covers the continuity of the thermal layer, the sealing and the sequence in which the surfaces are finished. Recticel Eurothane G consists of a PIR board faced on both sides with a gas-tight facing, plus 12.5 mm plasterboard. It is intended for suitable internal insulation applications. When selecting PIR boards for the assembly, draw the internal wall lining that connects the Eurothane G PIR with the 12.5 mm plasterboard in the actual cross-section. The masonry under Eurothane G must be prepared in accordance with its condition and the requirements of the new build-up, because the remaining layers must fit the same solution.

Light plasterboard face and layered section, accompanying the Eurothane G guide

Product construction in the context of the system

The individual layers must work together, because the factory bonding of the layers does not replace an assessment of the surface to which they are to be fixed. The adopted set should allow the composite to be matched to the existing building envelope and to the intended use of the interior. Add to the description of the solution the condition of the wall, the function of the room and the points where the new construction meets adjacent building elements, so that the complete set of layers can be verified.

Support and method of connection

The dimensions of the Eurothane G board are 2600 × 1200 mm. The PIR core has straight edges, while the longer sides of the plasterboard facing are bevelled, which enables the joints to be made.

Continuous polyurethane insulation requires a correct detail; in the description, include the bevelled long plasterboard edges and the straight edge of the Eurothane G insulating core. The plaster joint and the PIR core connection must be planned as two elements of the same junction before the layout is considered ready for execution. The instructions for the full field do not cover all terminations, because a correct joint on the visible surface does not automatically prove a correct PIR junction. The installation drawing should allow the 2600 × 1200 mm panels to be laid out with account taken of the two functions of their connection. Before you accept a substitute, check the position of the joints, the close fitting of the insulating part and the routing of services at the planned cut-offs in relation to the adjoining layers.

In Eurothane G, the geometry of the longer plasterboard sides serves to finish the joints, while the PIR core has a straight edge. These are two parts of one detail that should not be assessed solely from the painted wall side. The close fitting of the insulating part and the closing of the perimeter must be planned. Openings for services require similar attention. The composite simplifies the layer build-up, but it does not remove the task of connecting them correctly.

Compatibility of the protective layers

Using Eurothane G from the inside changes the thermal conditions of the wall. Gas-tight facings require the continuity of joints to be designed and an assessment of whether the wall will be able to dry out.

When selecting the protective layers, discuss a wall insulated from the inside whose external side remains in its existing condition. Before closing the wall, the source of moisture and the wall’s ability to dry out must be established for Eurothane G, because airtightness must also be achieved at the junctions between the different parts of the system. In the completed building element, the polyurethane foam needs protection, because the source of water in the wall may still be active despite the dry and even new gypsum surface. The adopted detail must allow the cause of the dampness to be eliminated and the ability to dry out to be verified before the wall is closed. In the description of the installation sequence, indicate traces of leaks, room ventilation and the detail where the insulation meets the floor and the ceiling; this information should be consistent with the documentation for the entire set.

Thermal effect of the entire building envelope

In the Eurothane G data, lambda 0.022 W/(m·K) refers to the PIR insulating part. The thickness of the gypsum plasterboard facing should not be treated as if it were part of the PIR core.

In the system calculation, take into account the difference between the total thickness of Eurothane G and the thickness of the PIR insulating part. In the Eurothane G calculation, lambda 0.022 refers to the PIR part and does not include the gypsum facing, so that parameters from different material variants are not combined. A mere change of material name does not produce equivalence, since treating gypsum and foam in the same way would overstate the thermal resistance of the composite. When comparing polyurethane boards in alternative arrangements, the insulation effect must be compared with the actual loss of space in the room. In both variants, compare the parameters of the PIR part, the share of the gypsum facing and the actual resistance of the entire product variant for the same function of the building element.

Range of mechanical and fire-related parameters

The B-s1,d0 class assigned to Eurothane G applies in a defined end use. It does not make the PIR foam non-combustible and does not determine the fire resistance of the entire building element.

The schedule of requirements for the system should clarify the plan for heavy fixings passing through the composite Eurothane G lining. The load of heavy equipment must be transferred through the built-in structure to a suitable substrate, and the scope of assessment must correspond to the actual configuration of the building element. The significance of the parameters changes with the scope of assessment, because the B-s1,d0 class relates to a specific application and does not describe the load-bearing capacity of suspended built-in structures. Before approving the structure, the fixing of the equipment must be designed independently of the fire assessment of the material. In the application documents, look for the type of anchors, the routing of installations and the documentation of the conditions of use of the composite in the given interior, and compare them with the designed layers.

Purchase in line with the adopted system

In the Eurothane G offer, state the thickness of the PIR part and the full scope of finishing works. Also determine the fixing materials, the method of making the joints and the solutions at the reveals.

When pricing the item “polyurethane insulation”, analyse the wall estimate covering Eurothane G as well as the preparation, fixing and finishing of the reveals. The Eurothane G offer should also cover the reveals, the perimeter of the built-in structure and works at the installations, so that the scope of purchase corresponds to the complete specification of the solution. An omitted item may come back as additional work, because the additional cost may result from repairing the substrate and from many short terminations at the openings. A well-described scope allows variants leading to equally complete and functional internal built-in structures to be compared. At the acceptance of the delivery and the works, confirm the scope of jointing, perimeter connections, wall repairs and the relocation of existing installation points, so that they agree with the agreed system.

7 branches. Materials closer to your project.

Sandwich-panel.pl map of seven branches offering sandwich panels, PIR boards and sheet metal
  • SEROCK — Dzierżenin 34 E [mapa]
  • BŁONIE — ul. Sochaczewska 138A [mapa]
  • RADOM — ul. Grobickiego 8 [mapa]
  • ŁÓDŹ — Natolin 8 [mapa]
  • OLSZTYN — Barczewo, ul. Prosta 9 [mapa]
  • WROCŁAW — ul. Jerzmanowska 10C [mapa]
  • GORZÓW WLKP. — ul. Zielona 33/34 [mapa]

Check prices and availability: +48 500 409 109

Free quote